As a part of the Development Plan the Contractor is required to submit an environmental impact assessment which shall include socio-economic conditions and an environment management plan et cetera (Model EPSC Article 7.1 (h) (ii)). Are there any caps on related costs?

Answer

Date Answered: 2009-08-18 13:08:54


These potential cost elements will be related to the prevailing conditions in relation to the particular field and the size of the development in question and cannot be generally estimated.